Timeline
-
Contractor procurement
April 2025Complete
-
Repair works commence
14 July 2025In progress
-
Repair works complete
October 2025 (complete date subject to drying time)Scheduled
Home > Our Services > Projects > St Peters Town Hall Complex Exterior Walls Repairs
Category: Venues and facilities
Managed by: City of Norwood Payneham & St Peters
Design: BB Architects
Contractor: Niara Built Pty Ltd
St Peters Town Hall complex is experiencing rising damp issues. The Council has engaged a qualified and experienced contractor to carry out repair works.
The project will take approximately three months to complete. However, the work will not take place every day, as the repair process includes necessary drying times between stages.
Most of the work will occur on the outside of the building. As a result, there will be minimal disruption to St Peters Library services and other users of the complex. All entrances will remain open throughout the repair period.
For safety, temporary fencing and bollards will be installed around work areas.
These repairs will help prevent future rising damp and support the long-term structural integrity and preservation of the complex.
We appreciate your understanding while we complete these important repairs.
Complete
In progress
Scheduled
$ 30,000
Contact Sylvia Soon
Contact role Building Assets Manager
Phone 08 8366 4555
Email townhall@npsp.sa.gov.au
Subscribe to receive updates on our projects